Project Status


13th Oct
Final Dinner with supervisor and sponser.


13th Oct
Project Exhibition.


4th Oct
Sponsor Presentation and handover.


30th Sep
Finished Technical Documentation and handed to supervisor.


14th Sep
Finished about 75% of the programming.
Currently programming for two other subsystems called Loading bay and Unloading Bay. Also working on technical documentation and user manuals.


16th Aug
Finished a beta version of the main module.
Implemented A stainless steel console to perform test.
User feedback was good.


24nd July
Still working on the main module.
Started on Loadin Module.


2nd July
Started work on the main module.


24th June
Started work on the design phase of the project.
Coding in Delphi.
Finished Module1.
This module allows the managers to add, remove and update to the staff database


30th May
Taken a leave from the project.
Preparations for exams.
Will resume project on the 24th of June


7th May
Delivered a presentation on the Project Specification
Submitted the Project Specification document


20th April
Received marks for the first presentation and documentation.


14th April
Started the analysis phase of the project. Currently gathering more information on the technologies to be used for the project.


9th April
Delivered a presentation on the Project Schedule
Submitted the Project Schedule document